Work carried out

3 ACTIVITIES · 12 PHOTOS · TUE 20 OCT

Level 3 EastGF-14
09:12

Blockwork courses 10–15 complete on the east wall. Wall ties in, ready for the next lift.

54.60
54.60
54.60
+3
Level 3 blockwork now 75%Logged
Level 2 WestGF-08
11:47

Lintels set over windows W2.04–W2.07. Cavity trays fitted to two openings.

54.60
54.60
54.60
+1
Level 2 cavity trays now 60%Logged
North elevationNE-02
14:05

Movement joint positions marked out ahead of facing brick, as asked by Peter Shaw (Corran Build).

54.60
54.60
North elevation set-out 20%Logged